The U.S. Navy is moving forward with plans to build a new multi-mission dry dock at Puget Sound Naval Shipyard in Bremerton, Washington, to address a critical lack of West Coast facilities capable of servicing large aircraft carriers. The project, part of the Shipyard Infrastructure Optimization Program, is backed by a potential $30 billion multi-award construction contract spanning five years plus options. Currently, only one dry dock on the West Coast (Dry Dock 6) can accommodate Nimitz-class carriers, and it lacks seismic resiliency and cannot fully handle the newer Ford-class carriers. The new dock will support depot-level maintenance for both Ford-class and Nimitz-class carriers, as well as other surface and subsurface vessels. The Navy expects the first task orders to include dredging, pier work, demolition of existing Dry Dock 3, and construction of new infrastructure such as substations, utility tunnels, and crane rails.
Source report
Concerned by the lack of docks on the West Coast capable of servicing large vessels such as aircraft carriers, the U.S. Navy is moving forward with plans to build a new dock at Puget Sound Naval Shipyard.
The Navy recently published a Sources Sought notice for a massive, multi-award contract — worth up to $30 billion — for the multi-mission dry dock.
Program Background
The dock is part of the Navy’s Shipyard Infrastructure Optimization Program, which aims to modernize the service’s four long-neglected shipyards:
- Portsmouth, Virginia
- Pearl Harbor, Hawaii
- Kittery, Maine
- Puget Sound Naval Shipyard & Intermediate Maintenance Facility
The contract is for five years, plus three one-year options.
Capability and Need
According to the Sources Sought notice:
"The Multi-Mission Dry Dock is a fully pressure-relieved dry dock capable of accommodating shipyard repair services for the newest Ford-class aircraft carrier, Nimitz-class carriers, and other surface and subsurface ships served by PSNS & IMF."
The project was spurred by the need to service Ford-class carriers on the West Coast. The Navy’s Multi-Mission Dry Dock website states:
"The Navy does not currently have the capacity and capability to perform depot-level maintenance on a Gerald R. Ford-class carrier in the Pacific Northwest."
Even servicing older carriers is limited at Puget Sound:
"The only dry dock on the West Coast able to accommodate a current Nimitz-class aircraft carrier is Dry Dock 6 (DD6), which does not meet seismic resiliency standards and cannot fully accommodate Ford-class carriers."
Contract Structure
The multiple-award construction contract (MACC) includes several task orders, typically ranging between $2 billion and $6 billion each. Smaller task orders may be issued for early contractor involvement and alternative technical concepts.
The Sources Sought notice specifies the project location:
"The focus of this MACC will be the construction of a new proposed Multi-Mission Dry Dock at PSNS & IMF, located at Naval Base Kitsap (NBK) Bremerton, Washington."
Located within the existing Dry Dock 3 and Piers 6 and 7, the project includes:
- Dry dock drainage, dewatering, and flooding systems
- A caisson
- Roadways and rail networks
- Portal crane track
- Access and egress elements
- Mechanical, electrical, and communications systems
- Support buildings
- Utility routing tunnels
- Demolition of facilities and utilities
Task Order Breakdown
The Navy expects the following task order sequence:
- Task Order 1: Dredging, plus work on piers, buildings, and utilities
- Task Order 2: Demolition of Dry Dock 3 and construction of the multi-mission dry dock
- Task Order 3: Infrastructure, including electrical substations, utility tunnels, and building crane rails
- Task Order 4: The dock caisson
Historical Context
Puget Sound has been a fixture for the Navy for more than a century:
- 1891: The Navy bought 190 acres for $10,000 (about $367,000 today) to create Naval Station Puget Sound
- 1900: The station became a shipyard
- Until 1941: It was the Navy’s only West Coast repair facility
"Between 1917 and 1969, Puget Sound Naval Shipyard constructed a total of 85 ships, including the largest vessels on the West Coast." — U.S. Navy
About the Author
Michael Peck is a correspondent for Defense News and a columnist for the Center for European Policy Analysis. He holds an M.A. in political science from Rutgers University. Find him at theuncommondefense.com. Email: mikedefense1@gmail.com.