Hut 8 Mining Corp shares rose nearly 12% after announcing a second long-term lease agreement for its Beacon Point AI data center campus in Texas. The 15-year lease covers 352 megawatts of IT capacity with the same high-investment-grade tenant from the first phase, bringing total contracted capacity at the campus to 704 MW. The agreement has a base-term contract value of $9.8 billion, fully commercializing the 1-gigawatt facility. Hut 8's total contracted AI data center capacity now reaches 949 MW, with aggregate base-term contract value of $26.6 billion and average annual net operating income over $1.75 billion. The second phase will support development of an AI factory using Nvidia's DSX architecture, with initial delivery expected in Q2 2028. CEO Asher Genoot highlighted the tenant's decision to double its footprint as validation of the company's power-first approach.
Source report
Source: Proactive Read Time: 3 minutes
HUT +7.98%
Hut 8 Mining Corp (TSX:HUT, Unlisted (US):HUTMF) shares climbed nearly 12% on Monday after the company announced a second long-term lease agreement for its Beacon Point AI data center campus in Texas, fully commercializing the 1-gigawatt facility and increasing its contracted data center portfolio.
Key Details of the Lease Agreement
- Duration: 15-year lease agreement
- Capacity: 352 megawatts (MW) of IT capacity
- Tenant: Same high-investment-grade tenant that signed the first phase lease at the campus
- Base-term contract value: $9.8 billion
- Total contracted capacity at Beacon Point: 704 MW (both phases)
Portfolio Impact
With this transaction, Hut 8's total contracted AI data center capacity rises to 949 MW across its portfolio, supported by 1,330 MW of utility capacity. The company reported:
- Aggregate base-term contract value: $26.6 billion
- Average annual net operating income (NOI): more than $1.75 billion across its contracted AI data center assets
Beacon Point Campus Overview
- Location: Nueces County, Texas
- Utility interconnection: 1,000 MW agreement with AEP Texas
- Status: Fully commercialized, with the full 1,000 MW capacity now contracted under two 15-year agreements
Phase 2 Development
The second phase lease will support the development of another 352 MW AI factory designed around Nvidia's DSX reference architecture for large-scale AI infrastructure. Initial Phase 2 data hall delivery is expected in the second quarter of 2028.
Financial Expectations
- Second lease contribution: $9.8 billion in cumulative net operating income over the base term, or approximately $655 million annually once stabilized
- Full Beacon Point campus: Expected to generate $1.31 billion in average annual NOI
- Renewal options: Three five-year renewal options under each lease could increase potential campus-level contract value to $50.2 billion if fully exercised
CEO Commentary
"The real test of our power-first approach is what our partners are willing to commit against it. Our tenant at Beacon Point chose to double its footprint at the site, the strongest validation an asset can receive. We took this greenfield site from first lease to full commercialization in just months. That speaks to the quality of the sites we originate, the credibility of our delivery, and the long-term orientation of our partnerships. The opportunity ahead of us is to apply the same model across our development pipeline."
>
— Asher Genoot, CEO of Hut 8
Development Approach
Hut 8 highlighted its "power-first" development approach, which involves securing energy capacity before building data center infrastructure. The Beacon Point project was initially developed around speed-to-power opportunities before being converted into a fully contracted AI data center campus.
Construction Timeline
- Construction activity is underway at the site
- Long-lead equipment has been procured
- Initial energization is still expected in the first quarter of 2027